Picture 1: Panoramic View of the Control Building of Weinan Natural Gas Co., Ltd
The project provides the control building with partial electric power supply, air-conditioning load in winter and summer and domestic hot water throughout the year.
With one 300 KW gas internal combustion generator set, one 300-kcal gas-fired hot water type lithium bromide cold and hot water unit, the 1250-kcal direct-fired gas turbine and the 0.7MW gas boiler to supply the energy demand.
The project is a multi-energy coupling project, which can generate electricity by itself to relieve grid pressure , saving energy and cost. As the first case of distributed energy project outside Beijing, it opened up the market for the company.
Picture 2:Site Selection of The Project Equipment